Tevatron

Bo Low Beta Separators HLS Installation - 50% complete

D0 Low Beta Separators HLS Installation - 25% complete

A0 Vacuum Upgrade - 99% complete

IPM installation - 70% complete. The Crystal Collimator has been installed

D4 Spool Replacement - 80%

D17 Separator Installation - 90% complete

D17 Separator Bake - Starts 10/22/04
D11 Separator Bake - Next week

Shimming 412 Dipoles - 82% complete

Unrolling Magnet - 80% complete

D0 Separator unroll - 100% complete
B0 Separator unroll - 0% complete

Linac

The Linac began sending beam to its dump at 1:10 PM on Wednesday, October 13, 2004.
Booster
There's some Booster vacuum problems slowing the start up, but there should be Booster beam by the afternoon of 10/22/04.

Antiproton Source

Debuncher Injection Area Beampipe and Quadrupole (Quad) replacement - Checkout in progress. Work on the last four D40 quads are in progress. Septum magnet pulse tested at full current, but need to be opened. The beam pipe is almost ready. The kicker beam pipe coating in progress.
Debuncher Motorized Quads Installation - ~90% complete
ARF1-1 Installation - 100% complete.

SO Cord Remediation - Parts of AP50 work in progress. Completion in two to three weeks

D/A Lines - alignment analysis in progress, cooling system measurements in progress, visual inspections after "as founds"

Beam Lines - Work in progress: AP1 magnet moves new VT108 & reconfigure vacuum windows, AP2 upstream vacuum will accessing beam stop

Other Work - Target Station, Alignment, LCW, and LLRF - all work on track

Main Injector/Recycler
Overall shut down progress - 80% complete

MI-30

Q307-309 Vacuum Modifications- 30% complete
Q303-305 Vacuum Modifications - 100% complete
MI-30 & 62
Correction Magnet Replacement - overall ~ 90% complete

MI-31

Electron Cooling overall - 58% complete

MI-10

Cooling Tank Repairs - ~85% complete

MiniBooNE

Horn Replacement - 100% complete,

NuMI

Power supply testing occurring during the evening. The horn may begin testing next week.


Accelerator Update Archive

More Information
For Tevatron luminosity charts and the current status of Fermilab's accelerators and detectors (live!), please go to Fermilab Now

Comments and Suggestions
What do you think about the Accelerator Updates? Please send comments and suggestions to: accelupdates@fnal.gov.



last modified 10/27/2004   email Fermilab

FRLsDFx9eyfrPXgV